Sign Off Report Procedure
Every morning the assigned Sign Off Manager checks the Sign Off Report and takes action to ensure fast sign Off.
The strategy is to:
a) Check the finish dates and action anything that has a finish date of 1 within 1 week of the current day.
b) Take action on anything that has not been signed off after 2 days (Art done on the 6th - not signed off by the 8th)
c)Take action on any sign off follow up that has not been responded to within 1 day of the sign off action.